2019-2020 Construction Project


BrEylWfQ
hvjFA6ZA
YdgNq46g
D8BA740F-FEAB-47C5-904A-C42CF109D977_1_201_a

October 9, 2019

Most of the last two weeks have been focused on masonry.  Masonry work has continued on the south and west walls of the construction site, but you’ll also notice that a lot of work has been done on the east side of the site, around the new stairwell that will connect the new facility with the Fr. Jones Room.  Masonry will continue to be the focus of our construction crew for the next several weeks.

October 22, 2019

Most of our work over the last two weeks has continued to involve masonry being erected against existing walls.  You’ll notice a lot of activity on the south wall of the new building (i.e. against the current intermediate and middle school classrooms).  They’ll continue this work for the next couple of weeks.

November 4, 2019

Over the last two weeks we’ve continued to work on the masonry outer walls of the new facility, with a lot of progress being made on the south and west walls.  We’ve also poured footings for what will be the east wall of the new gym.
In the coming weeks, we’ll finish the masonry along the west wall, install underground plumbing on the east side of the gym and pour the gym slab!